Installation:
Location Selection:
Choose a suitable location that complies with safety regulations and provides adequate ventilation.
Ensure there is enough space for maintenance and cooling.
Foundation:
The foundation should be level and vibration-resistant.
Transportation and Lifting:
Transport the transformer to the installation site using appropriate methods.
Lift the transformer carefully using suitable equipment.
Alignment:
Ensure proper alignment of the transformer on the foundation.
Connections:
Connect the transformer to the electrical system, ensuring correct phasing and proper grounding.
Oil Filling:
Fill the transformer with the recommended insulating oil, following manufacturer guidelines.
Commissioning:
Inspection:
Conduct a thorough inspection of the transformer, checking for any visible damage or defects.
Oil Testing:
Perform tests on the insulating oil to ensure it meets specified requirements.
Electrical Testing:
Conduct electrical tests, including insulation resistance, turns ratio, and impedance tests.
Protection System Testing:
Test the protection systems to ensure they operate correctly.
Load Testing:
Gradually apply load to the transformer to verify its performance under operating conditions.
Temperature Monitoring:
Control and Monitoring Systems:
Verify the proper functioning of control and monitoring systems.
Documentation:
Complete all required documentation, including test reports and commissioning records.
Training:
Provide training for personnel responsible for operating and maintaining the transformer.